Lindapter Girder Clamps provided a solution for the installation of large air conditioning units on several roofs.
Product: Type A & B Girder Clamps
Location: Wiesbaden, Germany
Project Value: €19 million
Steel Contractor: Huhle-Stahlbau
The Hessian Ministry for the Environment, Climate Protection, Agriculture and Consumer Protection buildings were built in 1989. Following a recent evaluation the buildings were deemed to no longer meet current energy performance requirements, therefore the decision was made to comprehensively renovate and expand them.
The client wanted to create highly energy efficient buildings by improving the performance of the façades and roofs in order to reduce energy consumption and CO2 emissions. As part of the project a modern and efficient heating and ventilation system was required, including the installation of large air conditioning units to the roofs of the buildings. The challenge was to find a suitable method of connecting these units to the roofs, and one that was easy to install.
The engineers decided to add an extra floor to the buildings which would house the air conditioning units. The additional floors were designed using a steel framework that was sat on the loadbearing concrete columns and suspended above the existing roofs.
Lindapter Type A & B Girder Clamps in a four-bolt connection were specified to connect the steel beams together. This would provide a structure strong enough to support the weight of the large air conditioning units. A hot dip galvanised (HDG) finish was also specified to provide a high level of corrosion protection.
Steel beams were fixed on top of the structural concrete columns using upstands. Additional steel beams were then connected on top at 90o using a location plate and a four-bolt configuration consisting of Lindapter Type A and B clamps. Installation was quick and easy as each bolt is simply inserted into the pre-drilled holes with the Type A holding the bolt captive while the nut on the Type B clamp is tightened with a torque wrench. The air conditioning units were then installed on the steelwork with all loads distributed to the structural columns.
Lindapter Type A & B Girder Clamps provided a drilling and weld free connection onsite that was quick and easy to install. The clamps are fully adjustable which gave the contractor the ability during installation to manoeuvre the beams into their final positions before fully tightening them.
Other improvements to the buildings included highly insulated façades with triple-glazed windows, integrated photovoltaic systems and planted elevations. All measures helped to improve the energy efficiency and reduce CO2 emissions.
Want to find out more about this product?
Watch the
installation video
How can we
help you?
Reasons to choose Lindapter
Save time and money
Clamping two steel sections together avoids time-consuming welding or conventional drilling and bolting.
Safer connections
On-site drilling and welding is avoided, removing the need for hot work permits and encouraging safer site conditions.
High strength
Lindapter clamps are manufactured from high strength materials to resist high load requirements and harsh environments.
Industry leading approvals
Lindapter has earned a reputation synonymous with safety and reliability, gaining multiple independent approvals.
Adjustable
Quickly align steel sections by sliding the section into the correct position before tightening the Girder Clamp to complete the installation.
Free connection design
Lindapter’s experienced Engineers can design a bespoke connection based on your specific requirements free of charge.
You must have a Lindapter account to access this content
Log in to your account
Register for an account
Don't have an account?
Click here to registerAlready registered?
If you have registered for an account but have not received your confirmation email, please click here to resend.
Headquarters
Lindapter Internationalnews